Standard work hours for this project will be Monday–Friday from 7:00 AM to 3:30 PM and Saturday from 8:00 AM to 4:00 PM unless otherwise noted. As we continue to place slab on decks within the building, there may be extended working hours Monday-Friday. Noise will be kept to a minimum and trucks will be asked to avoid idling.
Please be advised that starting to July 27th, we will be starting a second shift onsite (3:30-11 PM). Work will be concentrated to inside of the building with occasional trash-outs. Appropriate off hours permits have been pulled. This will be Monday-Friday through 8/31.
Check back here for the upcoming construction schedule for the first phase of Washington Village. If you have any questions or concerns, please do not hesitate to contact us at [email protected]
Upcoming Scheduled Gypcrete Pours:
*Work to commence around 12 PM and last 8-10 hours pending no interruptions. Off hours permit to be pulled for this work.
- Level 6A Week of March 13, 2023
- Level 4B Week of March 27, 2023
- Level 7B Week of April 3, 2023
- Level 6B Week of April 10, 2023
- Level 5A Week of May 1, 2023
- Level 5B Week of April 24, 2023
During the week of Monday, November 20th, the following activities will be occurring at the property:
- Punch list and final cleaning of the building are ongoing as we prepare to open the building.
- Fencing, hardscape and landscape installations are wrapping up around the site.
- The project site will be closed on Thursday, November 23rd.
- The Residential Leasing Team is providing tours of the building for prospective tenants. Tours can be scheduled Monday-Friday between 2:00pm – 6:00pm and on Saturday between 10:00am – 5:00pm. If interested, please visit https://livesouthstandard.com/ in order to sign up for a tour.
During the week of Monday, November 13th, the following activities will be occurring at the property:
- Punch list and final cleaning of the building are ongoing as we prepare to open the building.
- Fencing, hardscape and landscape installations are wrapping up around the site.
- The Residential Leasing Team is providing tours of the building for prospective tenants. Tours can be scheduled Monday-Friday between 2:00pm – 6:00pm and on Saturday between 10:00am – 5:00pm. If interested, please visit https://livesouthstandard.com/ in order to sign up for a tour.
During the week of Monday, November 6th, the following activities will be occurring at the property:
- Punch list and final cleaning of the building are ongoing as we prepare to open the building.
- Fencing, hardscape and landscape installations are ongoing; lighting and its associated infrastructure are being installed across the site. The majority of the sitework will begin to wrap up over the next few weeks.
- During the week, we will be paving New Street. This will occur during normal hours and last about one work day.
- The Residential Leasing Team is providing tours of the building for prospective tenants. Tours can be scheduled Monday-Friday between 2:00pm – 6:00pm and on Saturday between 10:00am – 5:00pm. If interested, please visit https://livesouthstandard.com/ in order to sign up for a tour.
During the week of Monday, October 30th, the following activities will be occurring at the property:
- Punch list and final cleaning of the building are ongoing as we prepare to open the building.
- Fencing, hardscape and landscape installations are ongoing; lighting and its associated infrastructure are being installed across the site. The majority of the sitework will begin to wrap up over the next few weeks.
- We will have a construction crew onsite on Saturday, November 4th. Construction will take place between 8 AM – 4 PM.
- The Residential Leasing Team is providing tours of the building for prospective tenants. Tours can be scheduled Monday-Friday between 2:00pm – 6:00pm and on Saturday between 10:00am – 5:00pm. If interested, please visit https://livesouthstandard.com/ in order to sign up for a tour.
During the week of Monday, October 23rd, the following activities will be occurring at the property:
- Finishes (i.e., appliances, countertops, light fixtures, furniture, etc.) are being completed throughout the interior of the building.
- Fencing, hardscape and landscape installations are ongoing; lighting and its associated infrastructure are being installed across the site. The majority of the sitework will begin to wrap up over the next few weeks.
- During the week, we will be paving New Street. This will occur during normal hours and last about one work day.
- We will have a construction crew onsite on Saturday, October 21st. Construction will take place between 8 AM – 4 PM.
- The Residential Leasing Team is providing tours of the building for prospective tenants. Tours can be scheduled Monday-Friday between 2:00pm – 6:00pm and on Saturday between 10:00am – 5:00pm. If interested, please visit https://livesouthstandard.com/ in order to sign up for a tour.
During the week of Monday, October 16th, the following activities will be occurring at the property:
- Finishes (i.e., appliances, countertops, light fixtures, furniture, etc.) are being completed throughout the interior of the building.
- Fencing, hardscape and landscape installations are ongoing; lighting and its associated infrastructure are being installed across the site. The majority of the sitework will begin to wrap up over the next few weeks.
- We will have a construction crew onsite on Saturday, October 21st. Construction will take place between 8 AM – 4 PM.
- The Residential Leasing Team is providing tours of the building for prospective tenants. Tours can be scheduled Monday-Friday between 2:00pm – 6:00pm and on Saturday between 10:00am – 5:00pm. If interested, please visit https://livesouthstandard.com/ in order to sign up for a tour.
During the week of Monday, October 9th, the following activities will be occurring at the property:
- Finishes (i.e., appliances, countertops, light fixtures, furniture, etc.) are being completed throughout the interior of the building.
- Fencing, hardscape and landscape installations are ongoing; lighting and its associated infrastructure are being installed across the site.
- Fencing along Old Colony and Dorchester St. have been pulled back against the building so pedestrians can now access these sidewalks.
- The general contractor is working a second shift (3:30pm – 11:00pm) Monday-Friday. The second shift personnel are dedicated to cleaning the building; this will involve the removal of materials from the building to the dumpsters on site. We apologize for any disturbance this may cause. The second shift is being undertaken to complete the building as expeditiously as possible.
- We will have a construction crew onsite on Saturday, October 14th to continue the work noted above – except for second shift. There will not be any second shift personnel working on Saturday, September 23rd.
- The Residential Leasing Team is providing tours of the building for prospective tenants. Tours can be scheduled Monday-Friday between 2:00pm – 6:00pm and on Saturday between 10:00am – 5:00pm. If interested, please visit https://livesouthstandard.com/ in order to sign up for a tour.
During the week of Monday, October 2nd, the following activities will be occurring at the property:
- Finishes (i.e., appliances, countertops, light fixtures, furniture, etc.) are being completed throughout the interior of the building.
- Fencing, hardscape and landscape installations are ongoing; lighting and its associated infrastructure are being installed across the site.
- Fencing along Old Colony and Dorchester St. have been pulled back against the building so pedestrians can now access these sidewalks.
- The general contractor is working a second shift (3:30pm – 11:00pm) Monday-Friday. The second shift personnel are dedicated to cleaning the building; this will involve the removal of materials from the building to the dumpsters on site. We apologize for any disturbance this may cause. The second shift is being undertaken to complete the building as expeditiously as possible.
- We will have a construction crew onsite on Saturday, October 7th to continue the work noted above – except for second shift. There will not be any second shift personnel working on Saturday, September 16th.
- The Residential Leasing Team is providing tours of the building for prospective tenants. Tours can be scheduled Monday-Friday between 2:00pm – 6:00pm and on Saturday between 10:00am – 5:00pm. If interested, please visit https://livesouthstandard.com/ in order to sign up for a tour.
During the week of Monday, September 25th, the following activities will be occurring at the property:
- Finishes (i.e., appliances, countertops, light fixtures, furniture, etc.) are being installed throughout the interior of the building.
- Fencing, hardscape and landscape installations are ongoing; lighting and its associated infrastructure is being installed across the site.
- The general contractor is working a second shift (3:30pm – 11:00pm) Monday-Friday. The second shift personnel are dedicated to cleaning the building; this will involve the removal of materials from the building to the dumpsters on site. We apologize for any disturbance this may cause. The second shift is being undertaken to complete the building as expeditiously as possible.
- We will have a construction crew onsite on Saturday, September 23rd to continue the work noted above – except for second shift. There will not be any second shift personnel working on Saturday, September 23rd.
- For the work occurring this Sunday, 9/24, electrical contractors will be onsite working at the exterior. They will be installing lights at the front and back of the building per Boston Fire Departments request. This additional work is required in order to achieve our TCO.
- The Residential Leasing Team is providing tours of the building for prospective tenants. Tours can be scheduled Monday-Friday between 2:00pm – 6:00pm and on Saturday between 10:00am – 5:00pm. If interested, please visit https://livesouthstandard.com/ in order to sign up for a tour.
During the week of Monday, September 18th, the following activities will be occurring at the property:
- Finishes (i.e., appliances, countertops, light fixtures, furniture, etc.) are being installed throughout the interior of the building.
- Fencing, hardscape and landscape installations are ongoing; lighting and its associated infrastructure is being installed across the site.
- Fencing along Old Colony and Dorchester St. have been pulled back against the building so pedestrians can now access these sidewalks.
- Dependent upon weather, signage will be installed on the building exterior.
- The general contractor is working a second shift (3:30pm – 11:00pm) Monday-Friday. The second shift personnel are dedicated to cleaning the building; this will involve the removal of materials from the building to the dumpsters on site. We apologize for any disturbance this may cause. The second shift is being undertaken to complete the building as expeditiously as possible.
- We will have a construction crew onsite on Saturday, September 16th to continue the work noted above – except for second shift. There will not be any second shift personnel working on Saturday, September 16th.
- The Residential Leasing Team is providing tours of the building for prospective tenants. Tours can be scheduled Monday-Friday between 2:00pm – 6:00pm and on Saturday between 10:00am – 5:00pm. If interested, please visit https://livesouthstandard.com/ in order to sign up for a tour.